Horizontal Directional Drill required for Telecoms services at New Lynn Rail Trench Project
Principal: Waitakere City Council, ONTRACK and Auckland Regional Transport Authority
Client: Telecom
Project: New Lynn Rail Trench Project
Contractor: Fletcher Construction Engineering
Service: Horizontal Directional Drilling

 

The New Lynn Rail Trench Project is a partnership between ONTRACK, Waitakere City Council and the Auckland Regional Transport Authority to lower rail track into a trench through the New Lynn town centre as part of the Western Line Duplication project.

The redevelopment will mean improved public safety, traffic improvements and station facilities. Two level crossings, including the notorious Clark St roundabout crossing, will be replaced with road bridges and up to three new road crossings built over the lowered track. It also includes redevelopment of New Lynn station as part of a new passenger transport Interchange.

This required all services to be lowered to a depth of 18m deep before the project could proceed.

Fletcher Construction Engineering performed some enabling works at the railway crossing in New Lynn and contracted PipeWorks to install a 500mm Ø HDPE SDR11 pipe that would be used as a Telecom service duct diagonally across the railway line, directly under the roundabout and the road crossing at the New Lynn Intersection.


Borepath of New Lynn Rail Crossing (Telecom Duct)

The 160m long, 18m deep pipeline was successfully installed using the Vermeer Navigator II, D100X120 horizontal drilling rig, capable of a 45.3 tonne push/pull and a 16.3kNm torque, owned by PipeWorks and at the time of installation the largest midi drill in New Zealand.

The congestion of other existing underground services in the area created challenges of its own. Minimalising the disruption to local businesses and the public in the area was also a priority.

The drilling process required the addition of bentonite lubrication resulting in a mini process plant being erected and operated inside the confines of the site establishment.  The photograph below illustrates the tight confines of the jobsite, allowing businesses to continue uninterrupted.

 

Aerial Photograph illustrates the tidiness of the drill site
Activity Duration
Set-up 2 days
Pilot Hole drilling 2 days
Reaming to 500mm Ø 2 days
Reaming to 700mm Ø 2 Days
Pulling in Product Pipe 5 hours
Disestablish site 1 day
Actual Durations achieved

 

News and updates

CIPP Records broken by PipeWorks during 2009 PipeWorks successfully installed the longest shots ... more >>

PipeWorks successfully completed a 900mm diameter, 306m long and 19.5mm thick CIPP liner ... more >>

 

PipeWorks imports Horizontal Directional drill... more >>

 

Horizontal Drill used at New Lynn Box Rail... more >>

 

PipeWorks wins the 2008 Safety Award... more >>

 
  All News Items >>
 
 
Contact
PipeWorks Ph: 0800 100316
18 Gabador Place or 09 5731901
P.O. Box 62077 Fx: 09 5731903
Mt Wellington  
Email: PipeWorks Customer Services
 
 
The Fletcher Construction Company Ltd trading as PipeWorks